Portable Changing Rooms: What Sports Clubs Need To Know

Written by Yusuf Vanat. Last Updated 6 September 2026.

Guide

A portable changing room is a factory built changing facility that is delivered complete and craned onto a prepared base, rather than built brick by brick on site. For most sports clubs the word portable describes the delivery method, not the intention: a single cabin can genuinely be moved again later, while a multi-unit building is sealed, connected and stays where it is put. This guide covers the hire or buy decision, realistic sizes, what the ground has to be like before anything arrives, and how long the whole thing takes. Prices for every layout are on our floor plans, and the cost guide explains what drives them.

What Is A Portable Changing Room?

Portable changing rooms are steel framed or timber framed buildings, fully fitted out in a factory with benching, showers, toilets and lighting, then transported to site and lifted into position. They arrive either as a single cabin or as several units bolted together to form a larger building. The alternative is a traditional brick build, which takes longer, costs more to programme and is far harder to fund in stages. Our guide on prefabricated cabins versus a brick build covers that comparison in full.

There is one distinction worth getting straight before you enquire anywhere, because it changes the quote you get:

Type What It Means In Practice
Single portable cabin One unit, delivered and craned into place, can be lifted and relocated later with crane access at both ends
Multi-unit modular building Two or more units joined, sealed and connected on site, portable at delivery but a permanent facility once installed
Hire unit Rented for a fixed term, returned at the end, usually a short term or temporary pitch solution

Most clubs who search for portable changing rooms turn out to want the second one. They are not planning to move the building; they want a permanent facility without a two year brick build. That is worth knowing before you compare quotes, because a hire fleet price and a purchase price are not comparable numbers.

Should A Club Hire Or Buy?

Hire makes sense when the need genuinely ends. A season while the main pavilion is rebuilt, a temporary second pitch, a construction compound. Buying makes sense when the facility is meant to last, which for a sports club is nearly always the case.

Consideration Hire Buy
Best for Under two years, temporary or seasonal use A permanent club facility
At the end of the term Unit is collected, club owns nothing Club owns an asset on its balance sheet
Specification Whatever is in the hire fleet Layout, fittings and team colours to suit the club
Grant funding Rarely fundable, no lasting asset Normally what funders want to see

The funding point is the one clubs underestimate. Football Foundation and council grants are aimed at facilities that will still be there in ten years, so a hire agreement is usually the wrong shape of application. Our funding guide and the free fundraising pack set out how clubs have actually paid for these buildings.

What Sizes Do Portable Changing Rooms Come In?

Sizes are driven by team count first, then by whether officials, a medical room or a social area are included. These are real buildings from our range, not indicative figures.

Building Size Provision
Single team 40ft x 10ft One team room with benching, toilets at each end
Two teams 30ft x 24ft Two team rooms with showers and toilets
Two teams plus officials 56ft x 16ft Two team rooms, officials room, showers and toilets
Two teams with canteen 72ft x 30ft Two team rooms, officials, kitchen and social area
Four teams plus officials 46ft x 46ft Four team rooms, officials room, showers and toilets

Inside the building, room sizing follows governing body guidance rather than what fits in the shell. The FA looks for at least 18 square metres per team room and 6 square metres for officials, with a minimum of 500mm of bench length per player. Our dimensions guide has the full set of figures, and accessible provision is sized separately under Approved Document M.

Every layout can be adapted. Sizes, fittings and internal walls all change to suit the site, so if your pitch side space is an awkward strip rather than a rectangle, that is a design question rather than a dead end. The 60ft x 12ft and 70ft x 12ft plans exist for exactly that reason.

What Does The Ground Need To Be Like?

This is the part clubs arrange themselves and the part that decides whether installation day goes well. A portable changing room needs a level, load bearing base: concrete pads under each corner and midpoint, strip foundations, or a full slab. It needs a mains water supply, foul drainage for the showers and toilets, and a single or three phase electrical supply sized to the building.

It also needs access. Buildings arrive by lorry and are craned onto the foundations, so the crane needs firm standing and clear reach, and the lorry needs a route in. We assess that with you before you order. At Weedon Sports Association two complete buildings were craned in during a single day because the access was right. One detail worth raising with your groundworker early: at the University of Greenwich the foundations were lowered so the finished floor sat flush with the surrounding tarmac, which removed the need for a ramp entirely. Our groundworks guide covers the specification in detail.

Do You Need Planning Permission?

Usually yes. A changing room building on a sports ground is normally treated as operational development, so most clubs apply for full planning permission, which takes around eight weeks to determine once validated. Smaller ancillary buildings can fall under permitted development depending on size, siting and use, and replacing an existing building of similar size and siting simplifies the position, but none of that is automatic and green belt or conservation designations change the answer. Confirm it with your local planning authority before committing to anything. We supply planning drawings, elevations and site layout plans for the application at no cost. The full detail is in our planning permission guide.

How Long Does It Take?

The building is rarely the slow part. Manufacture happens off site while the groundworks are prepared, so the two run in parallel. What sets the date is planning permission and funding, which is why we tell clubs to run the grant application and the planning application together: they take roughly the same time and finish at about the same point, ready for manufacture. Delivery and installation are then quoted by postcode, and we handle delivery, installation, connection and handover as one job.

If the need is more immediate than that, for example matchday toilets for a ground with none, our sister company Cabinworx holds brand new sanitary cabins and toilet units in stock for delivery in weeks rather than seasons. That is a different product to a changing room building, but it solves a different problem honestly rather than selling a club a facility it cannot yet fund.

Which Sport Are You Building For?

Layout requirements differ more than clubs expect. Rugby needs larger team rooms and heavier duty flooring, cricket wants a pavilion plan with a viewing aspect, football has the most prescriptive guidance through the FA. We have dedicated pages for football, rugby and cricket facilities, and every one of our floor plans lists its room sizes and a guide price so you can check a layout against your budget before you speak to anyone.

Frequently Asked Questions

Are Portable Changing Rooms The Same As Modular Changing Rooms?

In practice the words are used for the same thing. Portable describes how the building arrives, factory built and craned into place, rather than how often it moves. A single jackleg cabin can genuinely be lifted and relocated later. A multi-unit modular building is bolted together, sealed and connected to services on site, so it is portable at the point of delivery but stays put once it is in.

Should A Club Hire Or Buy A Portable Changing Room?

Hire suits short term needs such as a season of ground works or a temporary pitch, where the building leaves within a year or two. Buying suits a permanent facility, because hire charges on a changing room building typically pass the purchase cost within a few years and the club owns nothing at the end. Clubs applying for grant funding are usually buying, since funders want to see a lasting asset.

What Size Portable Changing Room Does A Club Need?

A single team room with benching and toilets fits in a 40ft x 10ft building. Two team rooms with showers and toilets need something closer to 30ft x 24ft or 56ft x 16ft depending on the shape of the site. Two teams plus officials, a kitchen and a social area runs to 72ft x 30ft. Team room sizing itself follows FA guidance of at least 18 square metres per team, with 500mm of bench length per player.

Do Portable Changing Rooms Need Planning Permission?

Usually yes. A changing room building on a sports ground is normally treated as operational development, so most clubs apply for full planning permission, which takes around eight weeks to determine once validated. Some smaller ancillary buildings fall under permitted development depending on size, siting and use, but nothing is automatic and the local planning authority should confirm the position.

What Groundworks Does A Portable Changing Room Need?

A level, load bearing base, normally concrete pads under each corner and midpoint, strip foundations or a full slab, plus a mains water supply, foul drainage for showers and toilets and a single or three phase electrical supply. The club appoints the groundworker and we supply the foundation specification showing exactly where the loads land.

Can A Portable Changing Room Be Moved To A New Site Later?

A single cabin can be lifted and moved, provided there is crane access and firm standing at both ends and the services are disconnected properly. Multi-unit buildings can be dismantled and relocated but it is a full project, with new foundations, new connections and resealing, so it is rarely worth doing for anything other than a forced move.

How Long Does It Take To Get A Portable Changing Room On Site?

Manufacture runs while your groundworks are prepared, so the critical path is usually planning permission and funding rather than the building itself. Clubs that already have permission and a base in place move much faster than clubs starting from scratch. Delivery and installation are quoted by postcode and buildings are craned onto the foundations, sometimes several in a single day.

Get A Layout And Guide Price For Your Ground

Tell us your sport, team count and site, and we will recommend a floor plan, confirm a guide price and supply planning drawings for your application.