Modular Sports Pavilion for the University of Greenwich
Case Study · University · 2017
As part of the University of Greenwich’s sports strategy at the Avery Hill campus, the university needed a changing facility to serve the variety of sports played there, with a medical area, an accessible shower facility and storage for essential equipment.
Project Details
| Client | University of Greenwich, Avery Hill campus |
|---|---|
| Building | 30ft x 72ft nine bay pavilion plus 20ft x 8ft self-contained unit |
| Facilities | 4 team changing rooms, accessible toilet and shower, medical room, storage |
| Year | 2017 |
| Installation | 2 weeks from delivery to handover |
What We Installed
Working with the university, we designed a nine bay modular changing pavilion with four team changing rooms, plus a single self-contained unit housing the medical room and an accessible shower. The ground workers lowered the foundations so the building sits flush with the surrounding tarmac, which both looks better and keeps every entrance step-free.
We liaised with the ground workers, project team and pitch provider throughout, and the whole installation from delivery to handover took two weeks, within budget and on time.



What the Client Said
“A rigorous process of detailed design led to the commissioning of the changing facility as an integral part of this sports pitch development. The facility proved to be of a high standard and there have been no quality issues since installation, which was logistically managed to precision. The University is quite rightly very proud of this initiative.”
Chris Andrew, Client Lead, University of Greenwich